A Construction Traffic Management Plan (CTMP) sets out how construction vehicles will reach, service and leave your site safely, and how pedestrians, cyclists and neighbouring road users will be protected while they do. CMP Construct prepares CTMPs compliant with borough council and TfL guidelines, either as standalone documents or alongside a full Construction Management Plan.

At a glance

Reviewed by
Borough highways officers
Often includes
Swept path analysis where access is tight
First draft
Usually 7–10 working days
Quote
Free and fixed, within 48 hours
On this page

    Councils attach CTMP requirements to planning permissions whenever construction traffic could affect the public highway: constrained access, nearby schools, bus routes, controlled parking zones, or simply the volume of deliveries a build will generate. The condition must be discharged before work can start on site: the plan is submitted, reviewed by highways officers and approved.

    What Our CTMPs Cover

    Every site is different, but a CTMP that highways officers approve first time typically addresses:

    • Approved construction vehicle routes to and from the site
    • Vehicle types, sizes and expected movements by phase
    • Site access and egress arrangements
    • Loading, unloading and delivery management
    • Banksman and traffic marshal provisions
    • Pedestrian and cyclist safety measures
    • Parking bay suspensions and temporary traffic orders
    • Swept path analysis where turning movements are tight

    Highway Lead Times by London Borough

    A CTMP usually depends on highway consents: road closures, parking bay suspensions, and scaffold, hoarding and crane licences. Each borough sets its own notice periods, and several will not process them until the plan is approved. Camden handles Temporary Traffic Restrictions only after CMP sign-off, Islington grants no licences or road closures before the CMP is signed off, Kensington and Chelsea issues licences only once the CTMP condition is discharged, and Tower Hamlets needs the discharged CMP with a road closure application. Typical lead times, from our borough guides:

    Notice periods for highway consents in each borough guide. On TfL red routes, licences come from TfL rather than the borough.
    BoroughLead times
    WestminsterRoad closures at least 8 weeks (10 for crane operations); parking suspensions 10 working days.
    CamdenTemporary Traffic Restrictions 6–8 weeks, processed only after CMP sign-off; parking suspensions 17 days ahead to avoid a short-notice charge.
    Kensington and ChelseaRoad and footway closures at least 6 weeks (up to 12 on major or TfL roads); permit bay suspensions 10 working days; licences only once the CTMP is discharged.
    SouthwarkRoad closures 12 weeks; scaffolding, hoarding and mobile cranes 15 working days; parking suspensions 7 days.
    IslingtonRoad closures at least 6 weeks (8–12 on strategic routes); licences 10 working days; parking suspensions 14 days; nothing granted before CMP sign-off.
    City of LondonRoad closures at least 12 weeks; scaffold and hoarding licences 4 weeks; parking suspensions 6 working days to process.
    LambethHighways licences 20 working days; parking suspensions at least 10 working days.
    Tower HamletsRoad closures 9 weeks from payment, with the discharged CMP; parking suspensions at least 7 working days.
    Hammersmith and FulhamScaffolding and hoarding 5 working days; cranes 10 working days, or 8 weeks with a road closure; parking suspensions 8 days to 4 weeks by size.
    WandsworthTraffic orders at least 8 weeks; mobile plant 2 weeks; scaffold, hoarding and skip licences 5 working days.
    HaringeyRoad closures at least 8 weeks; parking suspensions 2 weeks; skip licences 5 working days.

    Programme these alongside the CTMP rather than after it: a road closure that needs 12 weeks’ notice can hold up a start date long after the plan itself is approved.

    Written by Construction Professionals

    Our team plans construction traffic the way a contractor actually runs a site: realistic delivery schedules, vehicle sizes that match the methodology, and routing that a highways officer can approve without rounds of comments. That practical grounding is why our plans are trusted by leading developers and architects across London and the UK.

    Where your project also needs a full Construction Management Plan, a TfL-aligned Construction Logistics Plan or a Construction Environmental Management Plan for the noise, dust and environmental controls, we produce the documents together so routing, delivery strategy and site management stay consistent through council review.