Construction Management Plans in Islington
Every development in Islington is required to comply with the council’s Code of Practice for Construction Sites. Construction Management Plans are expected with major applications, basement schemes and any other site likely to cause disruption, and are completed on the council’s own pro forma after neighbours have been consulted on a draft. A Construction Logistics Plan is required alongside, Section 106 schemes pay a Code of Practice monitoring fee, and hoarding and scaffolding licences and road closures will not be granted until the CMP is signed off. Here is how the pieces fit together.
Islington at a glance
- Working hours
- 8am–6pm Mon–Fri, 8am–1pm Sat
- Lead times
- Section 61: 28 days; road closures: at least 6 weeks
- Document
- Council CMP pro forma, after neighbour consultation
- Monitoring fee
- Indicatively £350 per home or 100 sq m of commercial space
On this page
Islington’s Code of Practice and Monitoring Fees
The Code of Practice for Construction Sites (May 2018) remains the current edition. It applies to all types of building work, from demolition, site preparation and excavation to construction, refurbishment and maintenance, and the Principal Contractor carries ultimate responsibility for following it. Local Plan Policy S10 requires all developments to comply with it. Where compliance is a planning condition, failure to follow the Code can lead to legal action; on Section 106 schemes it is a formal obligation, and the developer prepares a site-specific Code of Practice response document for approval by the council’s Public Protection service before any works commence.
Rather than fixed project categories, Islington risk-assesses each site as low, medium or high risk for noise and vibration using the London Good Practice Guide method, scoring the programme length, the distance to the nearest neighbours and the type and duration of demolition, groundworks and piling. The risk level sets how much the Code expects: a formal Section 61 consent would not typically be needed on a low-risk site, is desirable on a medium-risk site and is highly recommended on a high-risk one.
Compliance with the Code, including a monitoring fee, is a standard Section 106 obligation in Islington. Fees are index-linked from the committee date to the date of payment, the Planning Obligations SPD’s worked example of 80 homes plus 350 sq m of employment floorspace comes to £29,225, and a site that breaches the Code, for example by carrying dirt onto the highway, faces further non-compliance charges. For applications validated from 30 April 2025, the SPD sets indicative fees of:
- £350 per residential unit
- £350 per 100 sq m of commercial floorspace, whether additional or replacement
- £175 per HMO, student, hotel or hostel bedroom
When Islington Requires a CMP and CLP
Local Plan Policy T5 (adopted September 2023) requires development proposals, particularly major developments and any other site that may cause disruption during construction, to identify and mitigate construction impacts, including through a Construction Logistics Plan, and the Planning Obligations SPD repeats that all developments should submit a CLP. Where an application has significant transport impacts, the CLP follows TfL’s two-stage model: an Outline CLP submitted with the planning application, and a Detailed CLP secured by condition and discharged before commencement.
Islington’s local validation requirements (April 2024) ask for a Construction Management Plan explaining how impacts on air quality, noise, vibration, waste, land, water and local ecology will be identified and mitigated, with three types of application:
- Major applications
- Applications involving basement development
- Any other site which may cause disruption during its construction
The Council’s CMP Pro Forma and Neighbour Consultation
Islington’s Construction Management Plan pro forma is published on the council’s website, and the validation requirements point applicants to it alongside the Code. It is a 45-question form, with the transport section completed together with the principal contractor, and the council asks for it as a Word document or searchable PDF, which it says makes the review quicker, sent to planning@islington.gov.uk. Where a condition requires the CMP, it must be approved before work starts, and Islington warns that failing to submit such details may invalidate the permission. Temporary traffic orders and hoarding or scaffolding licences can be applied for before the CMP goes in, but will not be granted until it is signed off. Neither the Code nor the pro forma sets a target time for approving the CMP itself, so the consultation and review need building into the programme.
A neighbourhood consultation on construction impacts must have taken place after planning permission is granted and before the first draft is submitted, separate from any consultation at planning stage. Everyone likely to be affected, including resident and business associations and ward councillors, should receive the draft CMP (or a link to it) and the site manager’s phone number and email, with adequate time to respond; on large sites this may mean two or more meetings with residents. The submission must show who was consulted, how, what they said and how the plan changed in response, or why it did not. Larger sites may also face a separate Section 106 obligation to run a Construction Working Group. The form also asks for several items that are easy to overlook:
- A Gantt-chart programme for each phase, the nearest affected receptors, and a scaled plan of the local highway network, parking bays and site access
- A plan of other construction sites nearby, showing how cumulative impacts will be managed
- Confirmation that mains power has been arranged so diesel generators are avoided, and evidence that staff are trained on BS 5228
- The GLA dust risk assessment carried out at planning stage, with its mitigation checklist appended
- Rodent control measures, with inspection records and receipts, and the date and key findings of the asbestos survey
- Considerate Constructors Scheme registration, and whether the site will sign up to the Building Mental Health charter (or similar) with trained Mental Health First Aiders on site
- Notice to the council when work starts, when it is about six months from completion and when it is complete
Working Hours, Deliveries and CLOCS
Noisy construction work is permitted 8am–6pm Monday to Friday and 8am–1pm on Saturdays, and must not take place outside those hours, including on Sundays and bank holidays, without the council’s prior permission. Out-of-hours permission must be sought from the Environmental Pollution, Policy and Projects team at least 7 days before the activity and is granted only in exceptional circumstances. Next to offices, restaurants and other businesses, the Code also advises negotiating quiet periods for the noisiest works, typically 10am–12 noon and 2pm–4pm on weekdays. Sites near the Emirates Stadium, or the tube stations serving it, must liaise with stadium management about match-day access and tell the council in advance about site activity on event days.
Vehicle movements are tighter still. The pro forma treats 9.30am–4.30pm on weekdays and 8am–1pm on Saturdays as generally acceptable for construction vehicles, and where a school is near the site or on the access route, deliveries are restricted to 9.30am–3pm on weekdays in term time. Islington is a CLOCS Champion: the Code requires contractors and sub-contractors to hold FORS Silver or higher and be registered as CLOCS Champions, the pro forma asks the developer to confirm the CLOCS Standard is written into its contracts, and vehicles without the correct registration or cyclist safety equipment should be turned away. No road in Islington may be used as a holding area for deliveries, there is no contractor parking on the highway anywhere in the borough, vehicles should arrive just in time with engines off while waiting, and traffic marshals should hold the qualifications for directing reversing vehicles.
Section 61, Noise, Vibration and Dust
Where a Section 61 prior consent is needed, the application should be submitted at least 28 days before construction starts, and Islington recommends sending a draft to the Environmental Pollution, Policy and Projects team at least a month before that. Islington’s older building stock adds to the risk: the Code warns that much of the borough’s historic property is likely to be sensitive to vibration, particularly where built directly on London Clay, and advises condition surveys of neighbouring buildings likely to be affected, even where no party wall agreement is in place. The CMP has to address these standards:
- Significant noise effects where site noise is more than 10 dB(A) above background levels, measured against a noise survey carried out before works start
- Recommended vibration limits of 1 mm/s at homes, schools, hospitals and laboratories, 3 mm/s at commercial premises and 5 mm/s at other unoccupied buildings
- An Air Quality and Dust Management Plan submitted before works start; the whole borough is an Air Quality Management Area
- Real-time dust monitoring: four monitors on a high-risk site and two on a medium-risk site, installed three months before works start, with real-time data and quarterly reports to the council
- Non-Road Mobile Machinery of 37–560kW meeting Stage IV across London (Stage V from 1 January 2030), registered on the London NRMM register, with an inventory and engine-plate records kept on site
- A named liaison officer, a complaints register and regular (typically monthly) newsletters to neighbours
Highways Licences, Road Closures and Parking Suspensions
The CMP must include a to-scale plan of hoarding, pedestrian routes, parking bay suspensions and the remaining road width; Islington prefers not to close footways, and using the highway for storage, site accommodation or welfare facilities is generally not permitted. Obstructions on red routes such as Holloway Road, Upper Street and City Road need permission from TfL instead. For Islington’s own licences, the notice periods and charges are:
- Scaffolding, gantries, hoarding, building materials and pit lanes: at least 10 working days’ notice, with each licence lasting up to three months; scaffolding, hoarding and materials licences need £10 million public liability cover
- Hoarding: a deposit of £100 per square metre enclosed plus £50 per metre run, and a management fee from £540 (deposits up to £750) rising to 40% of the deposit above £6,000; extensions must be applied for 14 days before expiry
- Mobile crane or aerial platform: at least 10 working days’ notice and £571 per licence, with £10 million public liability cover (£25 million for a tower crane)
- Road closures by temporary traffic order: at least six weeks’ notice, or 8–12 weeks on strategic routes, with a £4,770 management fee per three-month licence
- Parking bay suspensions: at least 14 days’ notice (10 days for Pay By Phone bays), charged to businesses at £320 for the first day, £83 per space on day two and £88.25 per space per day after that; exclusive use of a bay for more than six months needs a temporary traffic order instead
Basements, Listed Buildings and Conservation Areas
Local Plan Policy DH4 requires every basement application to include a Structural Method Statement signed and endorsed by a Chartered Civil Engineer (MICE) or Chartered Structural Engineer (MIStructE), and the Basement Development SPD (January 2016) asks for a Construction Management Plan with the application too. Residential basements are limited to one storey below the lowest original habitable floor, a maximum 3m floor-to-ceiling height, and less than 50% of the original garden or unbuilt area (or, if smaller, no more than 50% of the host building’s footprint outside it). The SPD limits expected damage to neighbouring buildings to CIRIA Category 2, requires by condition that the engineer who signed the statement is retained throughout construction, and makes construction in line with the Code a condition of any basement permission, with the CMP approved before any work starts on site. Where the site or its access route is near a school, the basement CMP must commit to keeping construction and delivery vehicles away during school arrival and departure times (8.30am–9.30am and 3pm–4.30pm).
Heritage adds another layer: around half of Islington is designated as conservation area, and the borough has roughly 4,500 listed buildings. Where a basement is permitted under a listed building, the CMP needs a statement and drawings showing how spoil will be moved on and off site, how the historic interior will be protected, and how any fabric temporarily removed will be protected and reinstated. For listed building consent involving structural works, the validation requirements may also call for a structural statement showing how the safety and stability of the building fabric will be ensured throughout the works.
How CMP Construct Helps in Islington
CMP Construct prepares council-compliant Construction Management Plans across Islington and more than 20 London boroughs. We draft most plans within 7–10 working days, submit in the format Islington Council expects, and handle officer comments through to discharge of your condition. Where your condition also asks for a Construction Traffic Management Plan (CTMP), a Construction Logistics Plan (CLP) or a Construction Environmental Management Plan (CEMP), we produce them as one consistent package. New to the process? Start with our complete guide to Construction Management Plans or see what a CMP costs.
Official Islington Guidance
The council documents below set out Islington Council's own requirements. We work to these day to day; they are linked here so you can verify any requirement directly:
- Islington Code of Practice for Construction Sites (May 2018)
- Islington Construction Management Plan pro forma
- Islington Planning Obligations SPD (April 2025): monitoring fees
- Islington street works highway licences
Frequently Asked Questions
Yes, for major applications, applications involving basement development and any other site likely to cause disruption during construction, under Islington’s April 2024 validation requirements, and every development must comply with the council’s Code of Practice for Construction Sites (May 2018). The CMP is completed on Islington’s own 45-question pro forma, published on the council’s website, and neighbours must be consulted on construction impacts before the first draft is submitted. A Construction Logistics Plan is also required, in two stages (outline with the application, detailed by condition) where transport impacts are significant.
Neither the Code nor the pro forma sets a target time for CMP approval, and the neighbour consultation has to happen before the first draft goes in. After that, Section 61 applications should be submitted at least 28 days before work starts (with a draft a month earlier), out-of-hours requests at least 7 days ahead, scaffolding, hoarding and crane licences at least 10 working days ahead, road closures at least six weeks ahead (8–12 weeks on strategic routes) and parking suspensions at least 14 days ahead. Licences and road closures will not be granted until the CMP is signed off, and real-time dust monitors on medium and high-risk sites must be installed three months before works start.
Under the Planning Obligations SPD, which applies to applications validated from 30 April 2025, the indicative fee is £350 per residential unit and per 100 sq m of commercial floorspace, and £175 per HMO, student, hotel or hostel bedroom. The SPD’s worked example of 80 homes plus 350 sq m of employment space comes to £29,225. Contributions are index-linked from the committee date to the date of payment, and the council can levy further charges if a site breaches the Code. Highways licences, road closures and parking suspensions are charged separately.
Noisy work is allowed 8am–6pm Monday to Friday and 8am–1pm on Saturdays, with none on Sundays or bank holidays unless the council gives prior permission. Out-of-hours work must be requested from the Environmental Pollution, Policy and Projects team at least 7 days ahead and is only allowed in exceptional circumstances. Construction vehicle movements are generally expected between 9.30am and 4.30pm on weekdays, and only until 3pm in term time where a school is near the site or its route.