Construction Management Plans in Lambeth

Lambeth asks for a draft Construction Management Plan or Construction Logistics Plan with every major application and with smaller schemes, including basements, that are likely to disturb neighbours or obstruct the highway. Unlike Westminster or Islington, Lambeth has no published code of construction practice and no CMP pro-forma. What the plan must cover comes from the council’s Local List, Local Plan Policy T7 and, for basements, Design Guide SPD Part 5, and the final plan is approved through a discharge-of-conditions application before work starts.

Lambeth at a glance

Working hours
8am–6pm Mon–Fri, 8am–1pm Sat
Approval time
Response within 8 weeks for discharge of conditions
Document
Draft CMP, CLP or CEMP with the application
Council fees
£765 per highways licence; £309 discharge fee
On this page

    When Lambeth Requires a CMP or CLP

    Lambeth Local Plan (2021) Policy T7 says major development, and any other development whose construction may significantly affect the surrounding public highway, should include a Construction Logistics Plan or Construction Management Plan “appropriate to the scale of the development”, showing how environmental, traffic and amenity impacts will be minimised.

    Lambeth’s Local Information Requirements (the Local List, issued December 2024 and still the current edition) turn this into a validation requirement: a draft Construction Management Plan, Construction Logistics Plan or Construction Environmental Management Plan must accompany:

    • All major development
    • Minor developments, including basements, likely to cause nuisance or disturbance to residential amenity during construction
    • Minor developments likely to cause a hazard or obstruction on the public highway during construction

    What the Draft Plan Must Cover

    The Local List expects the draft plan to set out the programmed duration, construction vehicle routing, the number and type of construction vehicles, site access and egress, and any temporary arrangements on the highway. It must also explain how construction traffic will fit with other construction traffic in the area, give details of participation in the relevant construction vehicle management groups, and cover dust, noise and vibration, construction waste, highway safety, protection of listed buildings and of off-site features such as trees, and safeguards for neighbouring homes and other sensitive uses. Large schemes delivered over an extended period should add a Construction Phasing Plan.

    Lambeth publishes no template of its own. The Local List points applicants to TfL’s freight guidance (TfL’s Construction Logistics Plan guidance is currently v1.2, April 2021) and to the Mayor’s Control of Dust and Emissions SPG (2014). Where a scheme involves demolition in a conservation area, of a listed or locally listed building, or in an Air Quality Management Area (which covers the whole of Lambeth), the Local List also requires a Demolition Method Statement setting out the demolition method, proposed working hours, environmental controls and demolition traffic.

    Construction Logistics, CLOCS and School Streets

    Under Policy T7, developers and their contractors are expected to meet the CLOCS standard and be registered with FORS or an equivalent scheme, and the Construction Logistics Plan must show that the impacts of other construction activity near the site have been considered and, where appropriate, coordinated with neighbouring developers and contractors. The Local Plan adds that construction vehicles should meet or exceed the minimum Direct Vision Standard and carry cycle safety equipment (side bars, blind spot mirrors and detection equipment), and that sites close to the Thames should consider moving materials and waste by river as part of the construction management plan.

    Delivery schedules also have to work around Lambeth’s School Streets: timed closures at school drop-off and pick-up times during term, enforced by barriers or ANPR cameras with Penalty Charge Notices. Exemptions are limited to residents and businesses with vehicles registered inside the zone and Blue Badge holders; contractors, tradespeople and delivery drivers are expressly not eligible, so a site on a School Street needs deliveries timed outside its operating hours. On TfL red routes, Lambeth must consult TfL on hoarding licence applications, and TfL can refuse them or set the deposit.

    Working Hours, Noise and Section 61

    Construction and building work in Lambeth is only allowed 8am–6pm Monday to Friday and 8am–1pm on Saturdays, and is not allowed on Sundays or bank holidays. Construction noise and vibration are controlled principally under the Control of Pollution Act 1974, separately from the planning system, and Lambeth’s Basements SPD notes that noise and pollution are enforced by the council’s Community Safety Team rather than Planning Enforcement. The CMP should commit to these hours and to best practicable means for noise, vibration and dust.

    Lambeth publishes no Section 61 guidance of its own, but under the Act the council has 28 days from receipt to decide a prior consent application, so any application needs to go in at least four weeks before the noisy works it covers. For basements, the SPD suggests quieter methods a CMP can commit to: hand digging for underpin excavation, silenced bored piling or push-in sheet piling rigs, and splitting rather than sawing or hammering when trimming concrete or masonry.

    Basements, Conservation Areas and Listed Buildings

    Local Plan Policy Q27 requires a Stage 1 (Screening) Basement Impact Assessment by a qualified professional with every basement application; the council can ask for further stages (2–4), and applicants pay for any independent assessment of them. The Local Plan expects BIAs to be prepared by a Chartered Engineer, MICE, C.WEM or CGeol, structural methodology statements to be certified by a chartered civil or structural engineer, and the engineer to be CARE accredited where a listed building is involved.

    Lambeth has 62 conservation areas covering around 30% of the borough. New basements to listed buildings need listed building consent, and the CMP must set out how features of heritage significance, such as paving, front steps, garden walls and railings, will be protected during construction. The SPD strongly encourages consulting neighbours and local amenity societies before applying, and notifying neighbours of noisy works and programme changes during construction. A basement extending under the public footway or carriageway also needs Technical Approval from the highway authority.

    Lambeth Design Guide SPD Part 5: Basements (adopted August 2023) requires a draft CMP with the planning application and a finalised CMP as a pre-commencement condition, reviewed by a suitably qualified and experienced engineer and following Considerate Constructors Scheme standards. The final CMP must cover:

    • Contacts, the programme, working hours, neighbour notification and a 24-hour emergency contact
    • Ground and structural stability, groundwater and movement monitoring, with an engineer inspecting critical works throughout
    • Security hoardings
    • Parking, deliveries, vehicle routing and the cumulative impact of other construction traffic
    • Dust, noise and vibration control, including wheel washing
    • Waste recycling and disposal
    • Protection of heritage assets

    Air Quality, NRMM and Construction Waste

    The whole of Lambeth is an Air Quality Management Area for nitrogen dioxide and PM10, and the Local List requires an Air Quality Assessment with all major and minor applications; in an Air Quality Focus Area (the Local Plan names five, including the A23 from Brixton to Streatham, Vauxhall Cross and Waterloo Road) even a minor scheme may need a full assessment. Lambeth conditions sites to meet the Mayor’s Non-Road Mobile Machinery emission standards when it grants permission, and works with Merton on the pan-London NRMM auditing project. Since 1 January 2025, machinery of 37–560kW on any London site must meet Stage IV as a minimum and generators Stage V, all of it logged on the NRMM register, with Stage V applying to all NRMM from 1 January 2030.

    Policy EN7 expects construction, demolition and excavation waste to be recycled on site wherever practicable, with 95% of construction and demolition waste reused, recycled or recovered and 95% of excavation waste put to beneficial use, so the CMP’s waste section should show how those targets will be met.

    Discharge, Highways Licences and Parking Suspensions

    The final CMP is approved through an application for approval of details reserved by condition, which Lambeth now takes through a pilot online service; the council says to expect a response in 8 weeks. The national fee from 1 April 2026 is £309 per request, or £89 for householder development.

    Highways licences for scaffolding, hoarding, fencing, gantries, stored materials, cabins and containers can only be applied for by the principal or building contractor, with a copy of its public liability insurance, and the notice period is 20 working days. For 2026/27 the fee is £765 per licence: six-week licences cover hoardings, scaffolding, fences, building materials, cabins and containers, and one-week licences cover cranes, hoists, gantries, cherry pickers and mobile towers. A highways engineer inspects the site and decides whether a refundable deposit is needed before the licence is granted, and licences cannot be renewed, so a fresh application must go in before expiry. A skip licence costs £80.

    Standard parking bay suspensions, including for a skip, need at least 10 working days’ notice, and short-notice bookings cannot be used for skips or renovations. Suspensions are only available within Controlled Parking Zones, each road needs its own application, extensions are treated as new applications, and the 2026/27 charges are a £98.83 admin fee plus £57.55 per space per day. Licence applications for materials in a parking bay can be delayed if the suspension has not been applied for, so the CMP, licences and suspensions are best programmed together as soon as permission is granted.

    How CMP Construct Helps in Lambeth

    CMP Construct prepares council-compliant Construction Management Plans across Lambeth and more than 20 London boroughs. We draft most plans within 7–10 working days, submit in the format Lambeth Council expects, and handle officer comments through to discharge of your condition. Where your condition also asks for a Construction Traffic Management Plan (CTMP), a Construction Logistics Plan (CLP) or a Construction Environmental Management Plan (CEMP), we produce them as one consistent package. New to the process? Start with our complete guide to Construction Management Plans or see what a CMP costs.

    Official Lambeth Guidance

    The council documents below set out Lambeth Council's own requirements. We work to these day to day; they are linked here so you can verify any requirement directly: