Skip to main content
CMP Construct

Construction Management Plans in the City of London

The City of London is not a London borough: the City of London Corporation manages construction in the Square Mile through its own Code of Practice for Deconstruction and Construction Sites. Instead of a borough-style CMP, sites agree a Scheme of Protective Works with the Corporation’s Pollution Control Team, major schemes add a Construction Logistics Plan, and developers pay an annual monitoring contribution. Autumn 2026 is a period of transition: City Plan 2040 is expected to be adopted by the end of the year, and a new Planning Obligations SPD raises the monitoring contributions and adds a separate fee for the logistics plan. The City’s working hours, quiet periods and highway rules remain among the tightest in London.

City of London at a glance

Working hours
8am–6pm Mon–Fri, 9am–2pm Sat
Lead times
Road closures 12 weeks; scaffold licences 4 weeks
Document
Scheme of Protective Works, plus a CLP on major schemes
Council charges
Monitoring £5,060–£53,820 in year one, rising under 2026 SPD
On this page

    The Code of Practice and Site Categories

    The Code of Practice for Deconstruction and Construction Sites is still the Ninth Edition (January 2019): the Corporation re-published it on its construction noise page in May 2026, and no tenth edition has been issued. It is the City’s guide to “best practicable means”, many City planning consents include conditions that refer to its standards, and the Code also serves as the City’s notice of its general requirements under Section 60 of the Control of Pollution Act 1974. Each site is categorised by the size of the development and the sensitivity of its surroundings, and the category sets what has to be agreed:

    • Category A (typically construction or deconstruction sites): prior consultation with the Pollution Control Team, a full Scheme of Protective Works approved by that team, and the full level of community engagement, including Ward Members
    • Category B (typically façade retention with internal works): prior consultation and a Scheme of Protective Works approved by the Pollution Control Team
    • Category C (typically refurbishment only): communication with neighbours, without a formal approval

    The Scheme of Protective Works and How It Is Approved

    The Scheme of Protective Works is the City’s equivalent of a borough Construction Management Plan, and the 2026 Planning Obligations SPD describes the condition as requiring a construction management plan prepared in accordance with the Code. Planning conditions often require the scheme to be approved, and no works may commence until it has been submitted to and approved by the Pollution Control Team. Neither the Code nor the Corporation’s construction noise page gives a determination period, and the Corporation says early contact with the Pollution Control Team is essential to reduce the risk of project delays. Where two or more sites operate close together, the Code also expects regular joint meetings with the City to manage their cumulative impact. The Corporation actively encourages every site to join its own Considerate Contractor Scheme, which has no membership fee and scores sites partly on compliance with the Code.

    Before each stage of work, the contractor must contact the Corporation’s Highways Division and the Pollution Control Team to agree the scope of the scheme and of community liaison, and on Category A sites the scheme must be presented to Ward Members, residents and businesses, with feedback answered in writing, before it is finalised. A full scheme covers:

    • The programme, with start and finish dates for the principal stages
    • A liaison and consultation strategy, with at least fortnightly communication with neighbours and a display board outside the site
    • A complaints procedure and log, which the City may inspect at any time, and a 24-hour contact number for the Pollution Control Team
    • Staff training, such as toolbox talks on noise, dust and sensitive receptors
    • Site plans showing receptors, access, wheel washing, monitoring locations, plant, water for damping down and the CLP haulage routes
    • Noise and vibration predictions at agreed receptors, baseline noise monitoring submitted before work starts, and trigger levels with response procedures
    • Vehicles and machinery, including NRMM compliance, working methods, and an Air Quality and Dust Management Plan

    Construction Logistics Plans and Vehicle Rules

    City Plan 2040 has not yet been adopted. The Inspectors’ letter of 23 September 2026 settled the last outstanding issue (the tall building contours near the Tower of London) and the Corporation expects to adopt the Plan before the end of 2026, but until then the Local Plan 2015 applies. It requires a Construction Logistics Plan for all major development and for any development that will cause significant transport impacts during construction (paragraph 3.16.11, under Policy DM 16.1). The submission City Plan 2040 names refurbishments alongside major developments (Policy VT1(5)) and expects outline details at application stage, with the full CLP required by condition (paragraph 10.2.8). The Planning Obligations SPD lists the full detailed CLP as due before commencement and sets its format: a PDF prepared in line with the CLOCS Construction Logistics Planning Guidance, with a site-specific Traffic Management Plan to the Red Book (Safety at Street Works and Road Works), swept path analysis, defined ingress and egress routes, hoarding and closure details, and the construction programme.

    The Code and the Corporation’s highway guidance notes add rules that apply on every site. Vehicles should enter and leave in forward gear wherever possible, every movement into and out of the site must be controlled by qualified traffic marshals, City streets must not be used as holding areas for waiting vehicles, lorries must observe the ban on travelling through the centre of the City except for access, and abnormal loads generally move on weekdays after 7pm or at weekends. The Code expects every fleet operator in the City to hold at least FORS Bronze, and all contractors to observe the Standard for Construction Logistics: Managing Work Related Road Risk. The Corporation is highway authority for every City street except the four TfL red routes (including Upper and Lower Thames Street, Bishopsgate and Farringdon Street), where licences come from TfL.

    Working Hours, Reduced Impact Hours and Section 61

    Where residents are likely to be disturbed, noisy work and ancillary activities such as deliveries are restricted to standard hours of 8am–6pm Monday to Friday and 9am–2pm on Saturdays, with no working on Sundays, bank holidays or other national holidays. Where businesses are likely to be disturbed, the City also imposes reduced impact hours of 10am–12 noon and 2pm–4pm on weekdays, giving commercial neighbours at least four hours a day without noisy work; during them, cutting and breaking out with power tools, impact fasteners and the loading of heavy materials are not usually permitted. Structurally transmitted noise that affects neighbours is barred between 9am and 5pm, party wall work and major works in partly occupied buildings are usually barred over the same period, and the Code treats an internal noise level of 65 dB(A) or more in neighbouring businesses as likely to cause annoyance.

    Any work outside standard hours, noisy work during reduced impact hours, and any early morning or evening deliveries need a Site Hours Variation Request, sent to the Pollution Control Team at least five working days ahead with predicted noise levels, mitigation and copies of the written notifications to neighbours. Work may only proceed once the sheet is countersigned, and an officer attending a complaint will stop noisy work without one. Concrete pours must be planned to finish within permitted hours, under a written protocol with the concrete supplier. Unusually, the City does not advise Section 61 consents, preferring this system of prior agreement, and it serves Section 60 notices where it considers them necessary.

    Highway Licences, Fees and Lead Times

    Skips and building materials may not be deposited anywhere on the highway in the City: they must be kept within a licensed hoarding or lifted directly from the vehicle into the site, and demolition methods that affect the highway must be submitted to the Corporation’s Highways and Pollution teams for approval. Most highway approvals start with a site meeting with the Highways Management team, charged at £340, and the Corporation’s charges from 1 April 2026 and its guidance notes for activities on the public highway set these fees and notice periods:

    • Scaffold and hoarding licences: application and fee at least four weeks before the agreed erection date; £620 for up to seven days, £720 for up to a month and £725 for each further month, per street (£1,465 a month with welfare facilities)
    • Road closures (temporary traffic orders): at least 12 weeks’ notice and £3,600 (£4,240 on a bus route), typically limited to weekends, bank holidays or 7pm–7am on weekdays
    • Mobile cranes and aerial platforms: a licence on four weeks’ notice, normally restricted to evenings and weekends, plus a mobile crane authorisation notice approved by the Pollution Control Team before the traffic appointment with Highways
    • Crane oversail: £3,050 per crane for the duration of the works, plus £790 a month for extensions; £1,465 per hoist or lifting beam
    • Traffic lights, stop/go boards and lane restrictions: an indemnity on four weeks’ notice, £450 (£540 on a bus route)
    • On-street concrete pumps: one week’s notice and a £4,770 fee for drainage inspections before and after pumping
    • Parking bay suspensions: six working days to process, plus a dispensation (£38 a day, three working days) for any vehicle standing in the bay

    Monitoring Contributions and the 2026 Planning Obligations SPD

    The Planning Obligations SPD adopted on 22 June 2026 will replace the Code’s fee schedule. Its adoption statement says it is implemented from 16 November 2026, while the Corporation’s planning guidance page (updated August 2026) says the new SPDs will be used in decision-making from the adoption of City Plan 2040, anticipated late 2026. Monitoring then rises to £58,500 on commencement and £52,250 a year after for large-scale majors, £33,625 and £28,000 for medium-scale majors, and £5,500 a year for minor developments, invoiced on commencement. No payment is due for a year in which no construction takes place if the City is told in writing in advance, and the unused part of the final year can be refunded on request. The SPD also introduces a fee payable on submission of the Deconstruction and Construction Logistics Plan: £10,000 plus £2,000 a month for the duration of the project on large schemes, £7,500 plus £1,000 a month on medium schemes, and £3,500 plus £1,000 a month on minor developments. Compliance with the Code, the scheme and the fees is secured by either a Section 106 obligation or a planning condition.

    Monitoring contributions follow the Code’s size bands: large-scale major development (200 or more homes, or 10,000 sq m or more), medium-scale major development (10–199 homes, 1,000–9,999 sq m, or a site of 0.5 hectares to under 2 hectares) and minor development (1–9 homes, or under 1,000 sq m). Until the SPD takes effect, the Code’s Appendix L sets the rates:

    • Large-scale major developments: £53,820 for the first year and £46,460 for each year after, covering twice-weekly site visits
    • Medium-scale major developments: £30,935 for the first year and £25,760 for each year after, covering weekly site visits
    • Minor developments: £5,060 a year; very minor works, such as those needing permission only because a building is listed, may be treated as out of category and charged nothing

    Air Quality, Dust and Heritage

    The City is an Air Quality Management Area for PM10 and nitrogen dioxide, and the Code expects every project to implement all possible dust mitigation and to explain any measure it considers unnecessary. Continuous particulate monitoring will normally be required on large sites next to sensitive premises such as homes, schools and St Bartholomew’s Hospital, with a PM10 alert threshold normally set initially at 150 µg/m³ over 15 minutes. Burning materials on site and explosive blasting are not permitted, and concrete crushers, long-arm demolition and on-site scabbling are not generally allowed. NRMM must be registered on the GLA register before work starts and meet the London NRMM Low Emission Zone standard: Stage IV now, Stage V from 1 January 2030. The Air Quality SPD (adopted June 2026, implemented from 16 November 2026) designates every construction site in the City as high risk, expects mains power to be secured as early as possible, and rules out generators installed solely to charge electric or hybrid machinery.

    Heritage adds a further layer. The City has 28 conservation areas and more than 600 listed buildings and structures, and much of it is designated as being of archaeological potential. The Code requires the contractor to confirm with the Corporation’s Development Management team whether the site contains a listed building, scheduled monument or archaeological remains, and what the planning permission and any listed building consent require; a programme of archaeological work is often a condition to be approved before work begins, and Historic England advises on scheduled monument consent. Trees on or near the site may be protected by a Tree Preservation Order, by conservation area status or by planning condition, and must be checked before work starts.

    How CMP Construct Helps in the City of London

    CMP Construct prepares council-compliant Construction Management Plans across the City of London and more than 20 London boroughs. We draft most plans within 7–10 working days, submit in the format the City of London Corporation expects, and handle officer comments through to discharge of your condition. Where your condition also asks for a Construction Traffic Management Plan (CTMP), a Construction Logistics Plan (CLP) or a Construction Environmental Management Plan (CEMP), we produce them as one consistent package. New to the process? Start with our complete guide to Construction Management Plans or see what a CMP costs.

    Official City of London Guidance

    The council documents below set out the City of London Corporation's own requirements. We work to these day to day; they are linked here so you can verify any requirement directly:

    Frequently Asked Questions

    Other London Boroughs

    Comparing boroughs? See construction working hours across London, basement rules in each borough and which councils expect their own CMP template, or go straight to another borough’s guide: