Basement schemes draw closer council scrutiny than most residential work: excavation beside neighbouring foundations, spoil removal through residential streets, and months of noise, vibration and dust. Most of the boroughs we work in ask for more than a standard CMP, from engineer-signed method statements to Basement Impact Assessments and building-movement monitoring. Here is what a basement CMP has to cover, and what each borough expects.

At a glance

Usually needed
A CMP or engineer’s method statement with the application
Signed by
A chartered civil or structural engineer in several boroughs
Size limits
Typically one storey, under half the garden
Quote
Free and fixed, within 48 hours
On this page

    What a Basement CMP Covers

    A basement CMP covers everything a standard Construction Management Plan does, with the excavation and its effect on neighbouring buildings at the centre. Expect it to set out:

    • The construction method and sequence: excavation, underpinning or piling, and the temporary works and propping that keep neighbouring structures stable
    • Ground, groundwater and building-movement monitoring, with an engineer inspecting the critical stages
    • How spoil leaves the site: vehicle sizes, numbers and routes, where skips and loading sit, and how the highway is kept clear (Wandsworth’s guidance, for example, advises avoiding grab lorries, which can block the road)
    • Noise, vibration and dust controls, including quieter methods such as hand digging for underpins, silenced bored piling and push-in sheet piling, which Lambeth’s Basements SPD suggests
    • Working hours and delivery times, which several boroughs restrict further for excavation and piling (see construction working hours in London)
    • Neighbour notification and liaison before and during the works, and a 24-hour contact
    • Protection of heritage features and historic fabric where the house is listed or in a conservation area

    Basement Rules by Borough

    Each borough sets its own basement policy and its own documents. In summary, with the full detail in our borough guides:

    Westminster

    Every new or extended basement, of any size, is at least a Level 3 project under the 2026 Code: a CMP with signed Checklist B, approved before work starts, and fortnightly council inspections. City Plan Policy 50 generally limits basements to one storey and to no more than 50% of the garden land.

    Basement rules in Westminster

    Camden

    Policy A5 requires a Basement Impact Assessment, most of them independently audited, and Camden will generally require a CMP, submitted in draft with the application. An Article 4 Direction covering the whole borough means every basement needs planning permission.

    Basement rules in Camden

    Kensington and Chelsea

    Policy CD11 limits basements to one storey and 50 per cent of the garden, with no excavation under listed buildings. Applications need a Construction Method Statement signed by a chartered civil or structural engineer and a draft CTMP, and any basement other than a minor one under 50 cubic metres makes the site Category 1 under the Code.

    Basement rules in Kensington and Chelsea

    Southwark

    Southwark has no stand-alone basement policy, but every new or extended basement needs a Basement Impact Assessment by a suitably qualified engineer or geologist, and the CMP has to carry its monitoring commitments through. No basements are permitted in Flood Zone 3b.

    Basement rules in Southwark

    Islington

    Policy DH4 requires a Structural Method Statement signed by a chartered civil or structural engineer, and the Basement Development SPD asks for a CMP with the application too. Residential basements are limited to one storey, a 3m floor-to-ceiling height and less than 50% of the original garden.

    Basement rules in Islington

    Lambeth

    Policy Q27 requires a Stage 1 Basement Impact Assessment with every basement application. The Basements SPD (August 2023) asks for a draft CMP with the application and a final CMP by pre-commencement condition, reviewed by a suitably qualified and experienced engineer.

    Basement rules in Lambeth

    Tower Hamlets

    The Local Plan 2031 requires a basement impact assessment for every basement, showing structural stability, safety from flooding and no harm to local hydrogeology, which matters on the Isle of Dogs and in the Lower Lea Valley. Under the Code, basement schemes also need a BS 5228 method statement.

    Basement rules in Tower Hamlets

    Hammersmith and Fulham

    A borough-wide Article 4 Direction means every basement needs planning permission. Policy DC11 limits new basements to one storey and to no more than 50% of the depth of the garden or host building, and requires a Construction Method Statement by a qualified structural or civil engineer, including a construction traffic management plan, with every application.

    Basement rules in Hammersmith and Fulham

    Wandsworth

    Policy LP6 allows a basement only one storey deep and, for homes, under no more than 50% of the rear garden, with stricter lightwell rules in conservation areas and no basements in Flood Zone 3b. A basement in a confined location triggers Wandsworth’s engineer-signed CMP at application stage.

    Basement rules in Wandsworth

    Haringey

    Policy DM18 requires a Basement Impact Assessment with every new basement or basement extension, carried out by independent assessors at the applicant’s cost, and expects the works to minimise noise, vibration and dust and not to harm road safety or bus operations.

    Basement rules in Haringey

    Impact Assessments and Method Statements

    Two documents usually come before the CMP. A Basement Impact Assessment tests whether the basement can be built without harm: ground and groundwater conditions, structural stability, flooding and drainage. Camden, Southwark, Lambeth, Tower Hamlets and Haringey all require one. A Construction Method Statement, or structural method statement, explains how the basement will be built and kept stable: Kensington and Chelsea, Islington and Hammersmith & Fulham require one with every basement application, signed by a chartered or qualified civil or structural engineer, and Westminster asks for a structural methodology statement self-certified by a suitably qualified engineer.

    The CMP has to be consistent with both. Southwark, for example, expects the Basement Impact Assessment to set out a method for monitoring ground conditions, water movement, subsidence and drainage, and the CMP to carry those commitments through, and Islington requires by condition that the engineer who signed the structural method statement is retained throughout construction.

    Neighbours and Party Walls

    Basement plans are judged heavily on how neighbours are treated. Westminster strongly encourages consulting neighbours before applying and may ask for evidence, Lambeth’s SPD strongly encourages consulting neighbours and local amenity societies, and Hammersmith & Fulham asks for the Construction Method Statement to be made available to neighbouring owners at the same time as the application. Separately from planning, excavating close to a neighbour’s foundations usually needs notice under the Party Wall etc. Act 1996, and the CMP’s methodology and monitoring should match what the party wall awards allow.

    Frequently Asked Questions